£17 million investment to improve Scarborough’s drinking water

4A_0514
Scarborough on the north east coast of Yorkshire.

Irton water treatment works will be modernised to improve drinking water and enable the site to meet the needs of future generations, Yorkshire Water announced on 20 March.

Irton works was built in the 1880s and some of the equipment is coming to the end of its life, says the utility.

Located at the end of Main Street in Irton, the works treats water from an onsite borehole and supplies between 15 and 23 million litres of drinking water to customers and businesses in and around Scarborough every day.

Last year the site was prepared for the construction phase of this project. Buildings were demolished to clear an area for the new process buildings and alterations were made to the pipework.

Morgan Sindall Sweco will design, manage and construct the project and will install new processes, including a pesticide removal plant, to enable the site to meet strict water quality standards.

Six tanks, each equivalent to the size of a hump backed whale (16m long), will be built offline and transported to the site this Autumn. 10 x 7m high granular activated carbon tanks, which remove organic constituents and impurities from the water using chemical absorption, will also be built offsite and transported to Irton.

Project Manager Jane Armstrong said, “The investment at Irton will ensure we continue to supply the best possible drinking water to our customers. We are trying to keep the impact on the community to a minimum by building the largest pieces of equipment offsite and transporting them to Irton.”

“Our partners Morgan Sindall Sweco will start setting up their site compound and welfare facilities during April so residents living nearby, or on Main Street, may start to notice an increase in site traffic then. We hope to finish the construction phase by the end of this year. This will be followed by the commissioning period, where we check all the new processes work and achieve what we need them to, which will take until Summer 2018 to complete.”